WSD contract No. 13/WSD/16

Mainlaying in Tseung Kwan O (NEC ECC Option C)

 Client : Water Supplies Department

Period : 2017-2021 (in Progress)

Laying of a 1 200 millimetres (mm) diameter fresh water main of about 10 kilometres (km) in length, connecting the proposed desalination plant at TKO to the existing TKO fresh water primary service reservoir

  • lay 8.3 km water main using Open Trenching Method along Carriageway and Footpath
  • lay 1.6 km water main using Trenchless Method