Remaining Engineering Infrastructure Works for Pak Shek Kok Development, Package 2D
Client : Civil Engineering and Development Department
Period : 2007-2011
Remaining Engineering Infrastructure Works for Pak Shek Kok Development, Package 2D
Client : Civil Engineering and Development Department
Period : 2007-2011
Concentric teamed up with Paul Y. to form a Joint Venture which was awarded the contract for the Engineering Infrastructure Works for Pak Shek Kok Development. Key deliverables included the construction of:
The project team initiated and provided an alternative design using precast pre-stressing method, including redesign of foundation, to replace the conforming in-situ construction of vehicular bridge. The alternative design was successfully executed to mitigate traffic impacts and risks to the busy Tolo Highway and MTR East Railway which respectively carries max. 6,300 vehicles per hour and 400,000 passengers every weekday. The biggest lifting crane of 600t capacity available in Hong Kong at the time was utilised to install the precast beams over the live railway tracks during restricted hours at nights.