CEDD Contract NE/2015/07

Signature Project Scheme in Sha Tin – Decking of Tai Wai Nullah in Sha Tin and Revitalisation of Shing Mun River Promenade near Sha Tin Town Centre

Client : Civil Engineering and Development Department

Period : 2016-2018 

Concentric was awarded a competitive contract by CEDD for the Signature Project Scheme in Sha Tin, Key deliverables included the construction of :  

  1. A deck approximately 2000 m2 over the Tai Wai Nullah, including all necessary ancillary and associated works;
  2. Atop of the deck of a Futsal pitch with ancillary and supportive facilities including boundary fencing and lighting;
  3. Barrier-free access ramps and stairs on both sides of the deck, connections between the deck and the adjacent footpaths; and
  4. A 2-3m wide extension at the upstream end of the deck; and
  5. Rebuilding the parapets of the two footbridges near Hong Kong Heritage Museum and Sha Tin Park with a new lighting system.