TDD Contract No. TP35/02

Remaining Engineering Infrastructure Works for Pak Shek Kok Development, Package 1 Subcontract Works: Pedestrian Subways

Client

Penta-Ocean Construction Co. Ltd.

2003-2004

10290013
01030010
01030074
CIMG3766
Dscn0874
DSCN3113

Concentric was selected to construct two pedestrian subways for part of the engineering works for Pak Shek Kok Development. The subways were built below tidal water level in the land formed by reclamation. Working sequence had to be carefully planned to overcome the tidal effect.