The works mainly comprise:

  • Construction of  a pedestrian subway  of  approximately 40 metres (m) in length and 4.2 m in width connecting the lift tower mentioned below to the concourse of MTR  Fortress Hill Station;
  • Construction of a lift tower with two lifts of approximately 33 m in height connecting the underground concourse of the MTR Fortress Hill Station, King’s Road and the access road between Fortress Garden and Fortress Metro Tower;
  • Construction of an elevated covered pedestrian walkway of approximately 25 m in length and 3.7 m in width connecting the lift tower mentioned above to the access road between Fortress Garden and Fortress Metro Tower;
  • Construction of a lift tower with two lifts at Fortress Hill Road of approximately 21 m in height, and an elevated covered pedestrian walkway of approximately 10 m in length and 6.2 m in width connecting the lift tower and Tin Hau Temple Road;

  • Construction of an elevated covered pedestrian walkway of approximately 33 m in length and 3.7 m in width across Tin Hau Temple Road, and a covered escalator with an  associated stairlift at Tin Hau Temple Road connecting to the elevated covered pedestrian walkway;
  • Construction of covered staircases, escalators and travelators along Wan Tin Path stairway;
  • Conversion of sections of the existing footpath at Fortress Hill Road into carriageway for relocation of an existing bus stop; and
  • Ancillary works including geotechnical, electrical and mechanical, drainage, landscaping, public lighting and utilities works, as well as construction of retaining walls and covered footpaths.